APPLICATION OF TIME COST TRADE-OFF METHOD TO COST AND TIME OPTIMIZATION ON INFLUENCE REDESIGN OF THE LOWER STRUCTURE (CASE STUDY: JEC JAVA MAIN EYE CLINIC CONSTRUCTION PROJECT @PASURUAN PHASE 1)

Moch. Aldy Doris Zhaputro (1), Helmy Darjanto (2), Fibria Conytin Nugrahini (3)
(1) Departemen Teknik Sipil, Universitas Muhammadiyah Surabaya, Indonesia,
(2) Departemen Teknik Sipil, Universitas Muhammadiyah Surabaya, Indonesia,
(3) Departemen Arsitektur, Universitas Muhammadiyah Surabaya, Indonesia

Abstract

ABSTRACT

An implementation period of construction projects would usually often experience the risk of delays in the project schedule. It can be caused by various obstacles that occur in the field even though the project has begun with careful planning and scheduling. The delay has a direct result in increasing the duration of implementation and also the cost of implementing the project. One way to overcome these delays is to implement acceleration in implementation so that the project can achieve the target as planned. However, it must also be accompanied by consideration of financing factors in order to achieve minimum costs with quality standards that remain achieved. This acceleration can be done, one of which is by adding working hours (overtime).


This research took a case study on the construction project of the JEC Java @Pasuruan Eye Clinic Main Clinic Building which experienced obstacles in foundation work, causing delays in project implementation. To overcome the problem of delay, the acceleration of the time needed would be calculated. The method that will be used is the Time Cost Trade-Off, in which the duration of the work is compressed to get a more profitable project implementation period in terms of time (duration), cost, and income.


This research implemented the Crashing Program by using an alternative method of adding working hours (overtime). Crashing was carried out on a critical trajectory obtained from the results of network planning analysis in Microsoft Project 2016. The results showed that by applying the Time Cost Trade-Off method with the alternative of adding 4 hours of work (overtime), the optimal duration of the project was 91 days with an optimal cost of Rp 2,072,972,561.


 


Keywords: Time Cost Trade-Off, Program Crashing, Addition of Working Hours.

Full text article

Generated from XML file

References

F. Pratasik, G. Y. Malingkas, T. T. Arsjad, and H. Tarore, “Menganalisis Sensitivitas Keterlambatan Durasi Proyek Dengan Metode Cpm (Studi Kasus: Perumahan Puri Kelapa Gading),” Jurnal Sipil Statik, vol. 1, no. 9, p. 129579, 2013.

A. T. Lagonda, P. A. K. Pratasis, and J. Tjakra, “Analisis Penerapan Manajemen Waktu Pada Proyek Konstruksi (Studi Kasus: Office and Distribution Center, Airmadidi, Minahasa Utara),” TEKNO, vol. 19, no. 78, 2021.

M. C. Winoto, K. Guwinarto, and S. Limanto, “Faktor Penyebab dan Dampak Keterlambatan Pelaksanaan Proyek Konstruksi Menurut Kontraktor Terhadap Indikator Performa Proyek,” Jurnal Dimensi Pratama Teknik Sipil, vol. 12, no. 1, pp. 56–63, 2023.

T. M. Sudarsono and O. Christie, “Analisis Frekuensi, Dampak, Dan Jenis Keterlambatan Pada Proyek Konstruksi,” Jurnal Dimensi Pratama Teknik Sipil, vol. 3, no. 2, 2014.

A. H. Rizal, S. Fay, and D. S. Krisnayanti, “PENGARUH BIAYA TERHADAP PENYEBAB KETERLAMBATAN PENYELESAIAN PROYEK KONSTRUKSI BENDUNGAN,” Jurnal Teknik Sipil, vol. 13, no. 01, pp. 55–66, 2024.

M. C. Winoto, K. Guwinarto, and S. Limanto, “Faktor Penyebab dan Dampak Keterlambatan Pelaksanaan Proyek Konstruksi Menurut Kontraktor Terhadap Indikator Performa Proyek,” Jurnal Dimensi Pratama Teknik Sipil, vol. 12, no. 1, pp. 56–63, 2023.

B. B. Setiawan and T. Trijeti, “Analisis Pertukaran Waktu Dan Biaya Dengan Metode Time Cost Trade Off (Tcto) Pada Proyek Pembangunan Gedung Di Jakarta,” Konstruksia, vol. 4, no. 1, 2012.

F. G. A. Ningrum, “Penerapan Metode Crashing Dalam Percepatan Durasi Proyek Dengan Alternatif Penambahan Jam Lembur dan Shift Kerja,” 2016.

C. T. O. F. F. D. P. JAM, “ANALISIS PERCEPATAN PROYEK MENGGUNAKAN METODE TIME COST TRADE OFF DENGAN PENAMBAHAN JAM KERJA LEMBUR DAN JUMLAH ALAT”.

L. A. Zahir, “STRATEGI OPTIMASI WAKTU DAN BIAYA MENGGUNAKAN TIME COST TRADE OFF (TCTO) PADA PEMBANGUNAN GEDUNG RUANG KELAS SMPN 1 BESUKI,” JURNAL DAKTILITAS, vol. 1, no. 2, pp. 36–51, 2021.

M. N. P. Wati, “Analisis Percepatan Proyek Menggunakan Metode Time Cost Trade Off dengan Penambahan Jam Kerja Lembur Optimum (Studi Kasus: Proyek Pembangunan Gedung Kantor Kelurahan Ketelan, Surakarta)“Project Acceleration Analysis Using Time Cost Trade-Off Method by,” 2015.

W. Hartono, M. N. P. Wati, and Sugiyarto, “Analisis Percepatan Proyek Menggunakan Metode Time Cost Trade Off dengan Penambahan Jam Kerja Lembur Optimum (Studi Kasus Proyek Pembangunan Gedung Kantor Kelurahan Ketelan, Surakarta),” e-Jurnal Matriks Teknik Sipil, pp. 1000–1004, 2015.

Authors

Moch. Aldy Doris Zhaputro
Helmy Darjanto
Fibria Conytin Nugrahini
fibriasantoso@gmail.com (Primary Contact)
Doris Zhaputro, M. A., Darjanto, H. and Conytin Nugrahini, F. (2024) “APPLICATION OF TIME COST TRADE-OFF METHOD TO COST AND TIME OPTIMIZATION ON INFLUENCE REDESIGN OF THE LOWER STRUCTURE (CASE STUDY: JEC JAVA MAIN EYE CLINIC CONSTRUCTION PROJECT @PASURUAN PHASE 1)”, Journal of Manufacturing in Industrial Engineering & Technology. Surabaya, Indonesia, 3(2), pp. 93–106. doi: 10.30651/mine-tech.v3i2.24621.